RAMS for roofers
Falls from height are the biggest cause of deaths in construction, and roof work is where many of them happen. A roofer's RAMS has to show how edges, fragile surfaces and the area below are controlled before anyone goes up.
Roofer preset: 14 hazards with controls, 9 steps of work, PPE and plant, ready to edit and download as a PDF.
Make RAMS for roofersHazards and controls
These are the hazards the roofer preset starts with. Residual risk is after the controls, on a 5 × 5 likelihood and severity scale.
Falls from roof edges
Roof work: edges and fragile surfaces · Who: Operatives · Residual risk: Medium
- Scaffold edge protection with guardrails, toe boards and brick guards in place before roof work starts
- Access by a properly secured ladder or scaffold stair tower
- Scaffold inspected by a competent person every 7 days and after bad weather; handover certificate kept
Falls through fragile surfaces (rooflights, cement sheets, old slates)
Roof work: edges and fragile surfaces · Who: Operatives · Residual risk: Medium
- Fragile surfaces identified before work and marked; no one walks on them
- Covers, staging or safety nets used where work is near fragile surfaces
- Crawling boards or roof ladders used on pitched roofs
Materials falling onto people below
Roof work: edges and fragile surfaces · Who: Client, public, other trades · Residual risk: Low
- Exclusion zone below the work area; signs and barriers
- Debris lowered in a chute or skip; nothing thrown from the roof
- Loose materials secured against wind
Weather: wind, rain, ice and heat
Roof work: edges and fragile surfaces · Who: Operatives · Residual risk: Medium
- Forecast checked daily; roof work stops in high winds, ice or heavy rain
- Sun cream, water and shade in hot weather
Falls from ladders or stepladders
Work at height: ladders and stepladders · Who: Operatives · Residual risk: Medium
- Ladders used only for short-duration (up to 30 minutes in one position), light work where a tower or podium is not reasonably practicable
- Professional ladders to BS EN 131, checked before use (stiles, feet, rungs, locking bars) and taken out of use if damaged
- Ladder set at 1 in 4, on firm level ground, tied or footed; extends 1 m above the landing point
- Three points of contact kept; no overreaching, belt buckle stays inside the stiles
- No work from the top three rungs of a ladder or the top two treads of a stepladder
Tools or materials falling from height
Work at height: ladders and stepladders · Who: Operatives, client, public · Residual risk: Low
- Area below kept clear or coned off
- Tools carried in a belt or pouch, not in the hands while climbing
- Nothing left on top of stepladders
Back and muscle injuries from lifting and carrying
Manual handling · Who: Operatives · Residual risk: Medium
- Loads assessed before lifting; mechanical aids (trolleys, sack trucks, hoists) used where possible
- Heavy or awkward loads lifted by two people
- Loads broken down into smaller units; materials delivered close to where they are needed
- Operatives shown good lifting technique
Fire caused by flames, heat or sparks
Hot work: soldering, brazing, torch-on and cutting · Who: Operatives, client, building · Residual risk: Medium
- Hot work permit issued where required by the client or principal contractor
- Combustibles removed or protected; heat mat used behind joints
- Suitable fire extinguisher at the point of work
- Area checked for at least 60 minutes after hot work ends; no hot work at the end of the day
Burns and fumes
Hot work: soldering, brazing, torch-on and cutting · Who: Operatives · Residual risk: Medium
- Gloves and eye protection worn; good ventilation
- Gas bottles stored upright, outside, away from drains and heat; valves closed after use; flashback arrestors fitted
Cuts, entanglement and flying particles from tools
Hand and power tools · Who: Operatives, others nearby · Residual risk: Medium
- Tools suitable for the task, maintained, with guards fitted
- Only trained and competent people use powered tools
- Blades and discs changed with the tool unplugged or battery removed
- Eye protection worn when cutting, drilling or grinding
Electric shock from tools and leads
Hand and power tools · Who: Operatives · Residual risk: Medium
- 110 V (centre-tapped) or battery tools on site; leads checked before use
- Portable equipment inspected and tested at suitable intervals
- Leads routed away from water and sharp edges
Disturbing asbestos in buildings built before 2000 (lung disease)
Asbestos · Who: Operatives, client, occupants · Residual risk: Medium
- Client asked for the asbestos register or survey before work; a refurbishment survey where work is intrusive
- Operatives have asbestos awareness training
- If suspected asbestos is found: stop work, keep people out of the area, tell the client and do not restart until it has been tested
- Licensed work only by a licensed contractor
Skin, eye or breathing harm from adhesives, sealants, solvents, cement and cleaning products
Hazardous substances (COSHH) · Who: Operatives, client · Residual risk: Medium
- Safety data sheets and COSHH assessments available for products used
- Less harmful products chosen where possible
- Gloves, eye protection and good ventilation as the data sheet says
- Wet cement and lime kept off skin; washing facilities used before eating
- Products stored in their original containers, lids on, away from children
Injury to the client, children, pets or the public
Working in occupied homes and premises · Who: Client, occupants, public · Residual risk: Low
- Work area agreed with the client and closed off with barriers or doors
- Tools, materials and chemicals never left unattended in reach of children
- Access routes and fire escape routes kept clear
- Occupants told about noisy, dusty or disruptive work in advance
- Services only isolated after warning the occupants
Sequence of work
- Check the weather forecast; do not start in high winds, ice or heavy rain
- Confirm the scaffold has been inspected and handed over, with edge protection in place
- Set up an exclusion zone at ground level with barriers and signs
- Get roof materials up by hoist or in small loads, never by carrying heavy loads up a ladder
- Strip the existing covering; lower waste in a chute or bags to the skip
- Check the deck and timbers; repair as needed
- Lay the new covering and flashings to the manufacturer's instructions (hot work permit for torch-on)
- Check for fire for at least 60 minutes after any hot work
- Clear the roof, gutters and ground area; inspect the finished work with the client
PPE
Safety boots, Hi-vis vest, Hard hat, Gloves, Eye protection, Knee pads.
Plant and equipment
- Scaffold with edge protection (erected by a scaffolding contractor)
- Access ladder, tied
- Materials hoist or gin wheel
- Rubbish chute and skip
- Gas torch, bottles and fire extinguisher (torch-on only)
- Battery cutting tools
Every job is different: delete what does not apply, add site-specific hazards and name the people responsible before you issue the RAMS.
Questions
Do I need a hot work permit for torch-on roofing?
Most main contractors and insurers require one. The permit records the fire precautions and the fire watch after the torch is switched off; the preset includes a 60-minute check.
Who checks the scaffold?
A competent person inspects it before first use, every 7 days and after anything that could affect it, such as high winds. Keep the handover certificate and inspection record.
Other trades: Plumbers and heating engineers · Painters and decorators · Carpenters and joiners · Plasterers and dryliners · Groundworkers and landscapers · all trades
Related: RAMS template · Method statement template · Toolbox talks
Checked against hse.gov.uk on 31 October 2026.