RAMS for groundworkers and landscapers
Groundworks bring together plant, excavations and buried services. Your RAMS needs to show how you locate services before digging, keep people away from moving plant and stop trenches collapsing.
Groundworker or landscaper preset: 9 hazards with controls, 8 steps of work, PPE and plant, ready to edit and download as a PDF.
Make RAMS for groundworkers and landscapersHazards and controls
These are the hazards the groundworker or landscaper preset starts with. Residual risk is after the controls, on a 5 × 5 likelihood and severity scale.
Being struck or crushed by moving plant
Plant: mini diggers, dumpers and other machines · Who: Operatives, public · Residual risk: Medium
- Plant operated only by trained, competent operators (CPCS, NPORS or equivalent)
- Daily pre-use checks recorded; seat belts worn
- Exclusion zone around working plant; a trained banksman for reversing and lifting
- No passengers; buckets lowered and keys removed when unattended
Collapse of trench sides; falls into excavations
Excavations and trenches · Who: Operatives, public · Residual risk: Medium
- Sides battered back or supported where there is any risk of collapse; no one in an unsupported trench where collapse could injure them
- Spoil, materials and plant kept back from the edge
- Edge protection or barriers around open excavations; covered or fenced overnight
- Excavation inspected at the start of every shift by a competent person
Striking hidden cables, pipes or gas mains when drilling, cutting or digging
Hidden and buried services · Who: Operatives, client · Residual risk: Medium
- Service drawings and client information checked before work
- Walls and floors scanned with a cable and pipe detector; buried services traced with a CAT and Genny
- Hand-dug trial holes before machine digging near services
- Water and gas located and the stopcock or ECV position confirmed before starting
Back and muscle injuries from lifting and carrying
Manual handling · Who: Operatives · Residual risk: Medium
- Loads assessed before lifting; mechanical aids (trolleys, sack trucks, hoists) used where possible
- Heavy or awkward loads lifted by two people
- Loads broken down into smaller units; materials delivered close to where they are needed
- Operatives shown good lifting technique
Breathing in silica dust (lung disease)
Dust: cutting, chasing and drilling masonry and concrete · Who: Operatives, client, others nearby · Residual risk: Medium
- Tools with on-tool extraction to an M- or H-class vacuum, or water suppression
- FFP3 mask, face-fit tested, worn as well as extraction
- Work area closed off and ventilated; others kept away
- Dust cleaned with an M-class vacuum, never by dry sweeping or compressed air
Hearing damage from noisy tools
Noise and hand-arm vibration · Who: Operatives, others nearby · Residual risk: Medium
- Quieter tools and methods chosen
- Hearing protection worn where noise is above 85 dB(A) or people must shout to be heard 2 m away
- Others kept away from noisy work
Hand-arm vibration (HAVS, white finger)
Noise and hand-arm vibration · Who: Operatives · Residual risk: Medium
- Low-vibration tools chosen and maintained
- Trigger time limited using the tool's vibration level and the HSE exposure points system
- Tasks rotated; breaks taken; hands kept warm
- Symptoms reported; health surveillance where exposure is regular
Being struck by vehicles reversing or delivering
Deliveries and vehicles on site · Who: Operatives, public · Residual risk: Medium
- Deliveries planned and booked; unloading area agreed
- Banksman used for reversing; pedestrians kept apart from vehicles
- Hi-vis worn in vehicle areas
Skin, eye or breathing harm from adhesives, sealants, solvents, cement and cleaning products
Hazardous substances (COSHH) · Who: Operatives, client · Residual risk: Medium
- Safety data sheets and COSHH assessments available for products used
- Less harmful products chosen where possible
- Gloves, eye protection and good ventilation as the data sheet says
- Wet cement and lime kept off skin; washing facilities used before eating
- Products stored in their original containers, lids on, away from children
Sequence of work
- Agree access, deliveries, skip position and working hours with the client
- Trace buried services with drawings and a CAT and Genny; mark them on the ground
- Set up site fencing and an exclusion zone around plant
- Carry out daily pre-use checks on plant
- Hand-dig trial holes near services; excavate with plant and support or batter trench sides
- Lay sub-base, drainage, slabs or blocks; cut with water suppression or extraction
- Keep excavations protected and covered at the end of each day
- Backfill, reinstate and clear the site
PPE
Safety boots, Hi-vis vest, Hard hat, Gloves, Eye protection, Hearing protection, FFP3 dust mask (face-fit tested).
Plant and equipment
- Mini digger and dumper (trained operators)
- CAT and Genny
- Plate compactor
- Disc cutter with water suppression
- Site fencing and barriers
Every job is different: delete what does not apply, add site-specific hazards and name the people responsible before you issue the RAMS.
Questions
What should I do before digging?
Get service plans, scan the area with a cable avoidance tool and genny, mark the services and hand-dig trial holes near them (HSG47).
When does an excavation need support?
Whenever it could collapse or people work in it. Batter the sides or use trench support, and inspect it at the start of each shift.
Other trades: Roofers · Plumbers and heating engineers · Painters and decorators · Carpenters and joiners · Plasterers and dryliners · all trades